1. Location
Poltava region, Kremenchuk city
2. Real Estate
Land plot: 9.5 ha (municipal ownership, under lease)
Total building and facility area: 23,550 m², including:
- Operational and leased space: 14,727.6 m²
- Unfinished construction (complete reconstruction for a meat processing plant): expanded from 5,730.9 m² to 7,000 m². 24% of construction works completed (demolition, columns, ceilings, bomb shelter). Project documentation available for both the meat plant and a 35/6 kV transformer substation with 2.7 MW capacity (approved by regional energy provider)
- Other unfinished or technically unusable buildings: 1,822.4 m²
Key Facilities Overview
|
Facility Name |
Area, m² |
Usage Status |
Technical Condition |
|
Workshop 1 |
3146,1 |
Leased |
Fully renovated, includes a new boiler house with 2 × 530 kW solid fuel boilers |
|
Workshop 2 |
1401 |
Leased (office in own use) |
Fully renovated |
|
Workshop 3 |
1592,6 |
Own use (cement mix production) |
Fully renovated (except façade) |
|
Workshop 4 |
535,9 |
Leased |
Fully renovated (except façade) |
|
Workshop 5 |
959,2 |
Leased |
Fully renovated |
|
Workshop 8 (1/2) |
1700 |
Own use (paving tile production) |
Fully renovated (1800 m²) |
|
Workshop 8 (1/2) |
1873,3 |
Not in use (no repairs: foundation, walls, roof) |
Requires reconstruction and repairs |
|
Workshop 10 |
878,8 |
Own use |
Fully renovated |
|
Warehouse |
168,7 |
Own use. Separate technical passport and extract |
Newly built |
|
Substation 11 |
77,8 |
1.3 MW (including equipment) |
Fully renovated with equipment |
|
Substation 13 |
23 |
Auxiliary (including equipment) |
Fully renovated (partially equipped) |
|
Boiler House |
189,5 |
Own use (used as storage) |
Fully renovated (except façade) |
|
Guard Post |
33,4 |
Own use |
Fully renovated |
|
Workshop 6 |
1345,2 |
Leased; part of meat processing plant project |
Roof repair |
|
Workshop 11 |
171,6 |
Own use (used as workshop building) |
Roof repair |
|
Garages |
589,5 |
Own use (garages) |
Roof repair |
|
Sewage/Water Pump Station |
10,7 |
Utility infrastructure, operational |
|
|
Water Pump Station |
31,3 |
Utility infrastructure, operational |
|
|
Workshop 9 |
316,5 |
Commissioned |
Not operational / requires repairs |
|
Workshop 7 (24% complete) |
7000 |
Building reconstruction. According to technical documentation, the original building area was 5,730.9 m², expanded to 7,000 m² under the reconstruction plan. Project documentation and partial construction for 7,000 m² are available. |
24% complete (columns, ceilings, demolition, bomb shelter, etc.) |
|
Building (separate site) |
1250,3 |
Unfinished construction |
Requires completion if needed (45% complete) |
|
Wastewater Treatment Plant |
255,6 |
Not in use, not required |
Not operational |
|
Total |
23 550 |
|
|
3. Utilities
- Electrical capacity: 1.3 MW (2 substations, 2 inputs), category II power supply
- Gas supply available (gas distribution point)
- Heating of selected industrial buildings and office: solid fuel boilers (512 kW)
- Video surveillance
- Water supply and sewage
- New concrete perimeter fencing
- 2 lighting masts
- 2 guarded entrances/exits with gates
- New energy-efficient lighting installed throughout the premises
- Agreement in place with KNESS to install rooftop solar power stations by 2026
- Security
- Asphalt pavement across the territory
4. Building Materials Production
The production of cement-based dry mixes, paving tiles, and decorative PVC products includes the following product groups (formulations for each line developed in accordance with Ukrainian national standards – DSTU):
- Paving tiles
- Cement-based dry mixes (tile adhesives, toppings, etc.)
- PVC corner profiles and mesh-reinforced PVC corner profiles
Product catalog available for download: Dry Mixes / Building Products
Sales channels: Retail and wholesale distribution through “Domovyi”, Epicentr, Nova Linia, construction crews in Kremenchuk, Market 360, BC Ferrostroy, BC Europebud, BC Zhitloinvestbud, Construction Guild (Kyiv), and others.
Production Equipment
1. Paving Tile Workshop:
- Hess vibropress
- Promax batching and mixing unit (BRU)
- Technical pallets
- Molds
- Feeding and reloading unit
- Linde forklift (1.5 t, 2 pcs)
- Hitachi forklift
2. PVC Products Workshop:
- Extrusion lines
- Gluing machines
- Hot-cold mixer
- Pulverizer
- Miscellaneous (molds, attachments, etc.)
3. Cement Dry Mixes Workshop:
- Equipment set (furnace, mixer, 3 silos, packing line)
- Renault Master truck (1.5 t capacity)
- Trademark “ALDI” (at final registration stage)
Personnel: 25 employees
Key staff: chief accountant, chief power engineer, production manager/technologist, head of sales, vibropress and BRU operators
Business Development Potential
The site is located in an industrial zone within the city. The paving tile segment has significant growth potential, especially for industrial paving tiles. The main client is Poltava GOK, and currently, there are no producers of industrial paving tiles in Poltava, Cherkasy, Kharkiv, or Kirovohrad regions.
5. Investor Offer
You are invited to consider the following options:
- Purchase of the entire real estate complex and the construction materials production business — $13,500,000 (sale of corporate rights), which includes:
• The main real estate complex
• The unfinished construction project with documentation for a meat processing plant
• The business related to the production of construction mixes, PVC products, and paving tiles - Purchase of the unfinished meat processing plant (real estate):
• with a turnkey meat-processing equipment package: $9,000,000 including VAT
• without meat-processing equipment: $5,000,000 including VAT - Purchase of 50% of the real estate complex, without the business.
• Real estate complex with an area of 8,000 m² or 12,000 m² (including the unfinished construction): $8,000,000 including VAT - Partial sale of the complex is possible — additional options available upon request.